Advanced Seafood Processing Complex in Busan

History

Advanced Seafood Processing Complex in Busan > Information > History
Advanced Seafood Processing Complex of Busan
  1. 2014
    • 02

      opening ceremony(on Feb 21).

  2. 2013
    • 07

      The construction of the Complex is completed (on July 31).
      Operation Management of Advanced Complex of Processed Seafoods (on July 10).

    • 01

      The plan for operation of the Complex is prepared.

  3. 2012
    • 02

      The first work (for reclamation) is completed.

  4. 2011
    • 10

      The explanation meeting on the construction of the Complex is made to Seafood processors.

    • 06

      The official work starts.

    • 03

      A construction permit is issued by Seo-gu Office.

  5. 2010
    • 12

      The actual plan for work at the port is approved.

    • 10

      Opening ceremony is conducted.

    • 06

      The permit is allowed for the construction of non-controlled port work.

    • 05.10 / 05.19

      The contract is made for first work and the work starts.

    • 03

      Daewoo E&C consortium is selected as a proper designer.

    • 03 ~ 12

      The environmental impact assessment is conducted and the coordination with related authorities is completed.
      - The future accident impact is reviewed
      - The traffic impact is analyzed and the actions for improving the traffic are taken
      - The cultural remains are researched
      - The environmental impact is assessed

  6. 2009
    • 11

      The basic plan service is completed.

  7. 2008. 07 ~ 2009. 03
    • The basic plan service is completed.